Tuesday, 9 September 2014
Alternative Power Solution Limited v Central Electricity Board and another
[2014] UKPC 31
Privy Council
Appeal No 0035 of 2013
JUDGMENT
Alternative
Power Solution Limited (Appellant)
v
Central
Electricity Board and another
(Respondents)
From the Supreme
Court of Mauritius
before
Lord Mance
Lord Clarke
Lord Sumption
Lord Hodge
Lord Toulson
JUDGMENT
DELIVERED BY
LORD CLARKE
ON
9th September
2014
Heard on 2nd
April 2014
Appellant
Aidan Casey
(Instructed by Sheridans Solicitors)
Respondent
Desire Basset SC
(Instructed by Blake Morgan
Solicitors)
Respondent
Rishi Pursem SC
Nadeem Lallmamode
(Instructed by Carrington and
Associates)
LORD CLARKE:
Introduction
1. This appeal centres on the fraud exception to the obligation
of a bank to make a payment under a letter of credit. It arises out of an injunction granted by P
Lam Shang Leen J (“the judge”), sitting in the Commercial Division of the
Supreme Court of Mauritius, by which he restrained the second respondent
(“Standard Bank”) from making a payment to the appellant (“APS”) under a letter
of credit which had been issued in favour of APS. The letter of credit was issued as the means
of payment under a contract of sale between APS and the first respondent (“the
CEB”). The appeal arises out of an order
made by the judge on 18 February 2011 in which he continued and, as it was put,
made interlocutory an interim injunction which he had first granted against
Standard Bank ex parte on 21 December 2010.
APS appealed to the Court of Appeal in the Supreme Court, which is part
of the Supreme Court in Mauritius. The
appeal was heard by YKJ Yeung Sik Yuen CJ and Matadeen SPJ but the appeal was
dismissed on 14 August 2012. APS now
appeals to the Board pursuant to leave granted by the Court of Appeal.
2. The reasoning of the judge and the Court of Appeal were not
the same but they both held that the CEB was entitled to an injunction
restraining Standard Bank from paying APS under the letter of credit because there
was sufficient evidence of fraud on the part of APS to the knowledge of
Standard Bank to engage the fraud exception.
As appears below, the Court of Appeal went further than the judge in
this regard. It was submitted on behalf
of APS and Standard Bank that both the judge and the Court of Appeal were wrong
to conclude that there was sufficient evidence of fraud to engage the
exception.
The contract
3. Not all the documents which might be relevant to the
contract between APS and the CEB were before the courts below or before the
Board. However, a sufficient number were
put in evidence so that a clear picture emerges. During the course of 2010 there was a tender
process during which APS bid for the supply of 660,000 compact fluorescent
lamps (“CFLs”) or bulbs to the CEB. The
process led to a “Contract Agreement” dated 3 September 2010, which recorded
that the
CEB had accepted APS’ bid
for the supply of the CFLs for the total price of Rs23,370.000, which was
equivalent to US$763,725.50. The price
was expressed to be DDU, which the Board understands to mean delivery duty
unpaid.
4. The contract provided, so far as relevant:
“2. The following documents shall constitute the
Contract between the Purchaser and the Supplier and shall be read and construed
as an integral part of the Contract:
(a) this
Contract Agreement;
(b) Purchaser’s
Letter of Acceptance ref: CMO/CA3051/LOA/APSL dated 26 August 2010;
(c) The
General Conditions of Contract (GCC) for Procurement of Goods and the Special
Conditions of Contract (SCC) and the bidding document CA/3051 dated 23 December
2010 [sic];
(d) Supplier’s
Technical and Financial Proposals dated 19 January 2010 and replies to all
Purchaser’s clarifications; …
3. This Contract shall prevail over all other Contract
documents. In the event of any discrepancy or inconsistency within the Contract
documents, then the documents shall prevail in the order listed above.”
5. The Letter of Acceptance referred to at 2(b) provided, so
far as relevant:
“You are hereby requested
to: … (d) sign and return the attached Contract Document; … (f) manufacture and
supply the above CFLs as per Technical Specifications contained in Part 2 of
our bidding document OAB No.CA/3051 and as per your offer dated 19 January
2010…”.
6. As
to 2(c) the only section of the GCC in evidence was section 4, “Inspections and
Tests”, which provided, so far as relevant:
(a) The
CEB… shall have the right to inspect and/or to test the equipment to confirm
their conformity to the Contract specifications. The CEB shall notify the Supplier in writing,
in a timely manner, of the identity of any representatives retained for these
purposes.
(b) The
inspections and tests shall be conducted on the premises of the Supplier…”
The SCC were in
evidence. They were expressed to
supplement or amend the GCC and, where there was a conflict, to prevail over
the GCC. They provided inter alia for
ICC arbitration in respect of all disputes arising in connection with the
contract (GCC 10.2); for specific details of the “Shipping and other Documents
to be furnished by the Supplier” (GCC 13.1); if goods were to be supplied from
abroad, for payment by cash against goods or by letter of credit “at Supplier’s
option” (GCC 16.1); and for the provision of a “performance security” (GCC
18.1). The SCC further provided:
“The inspections and tests shall be: The Manufacturer
shall carry out all routine tests prior to shipment in the presence of the
Purchaser’s Representative/designated independent inspector as may be
prescribed by the latter to the successful bidder, after Acceptance of offer”
(GCC 26.1); and “The inspections and tests shall be conducted at: the Factory”
(GCC 26.2).
7. As to 2(d), the “Technical and Financial Proposals dated 19
January 2010” were not in evidence in their entirety. However it was apparent that in its bid APS
had identified the proposed manufacturer as Ningo Blunt International Trade Co
Ltd. There was in evidence one request
for clarification issued by the CEB, namely Clarification No 2, together with
APS’ reply to the request. The request
referred to APS’ bid document and included these requests:
“a. Please provide the manufacturer’s name, models and
types of all
Lamps proposed as per the manufacturer’s/supplier’s
catalog;
b. Please
provide the ELI/EST certificate for each of the above proposed models/types.
c. Please
submit the Manufacturer’s Authorisation Form duly signed by the Manufacturer…”
8. APS’ replied to the request for Clarification No 2 under
cover of an email of 8 February 2010, which referred to Philips but made it
clear that Philips was not the contract manufacturer. Thus it stated:
“(a)…Philips (China) Investment Company Limited is the
brand owner… In the present tendering process, we would be supplying OEM/ODM
product for CEB Mauritius out of a plant manufacturing for Philips and
satisfying technical and performance requirements with minor deviations as per
specifications laid down in the technical documents. However if you require
specifically Philips brand on a co-branding exercise with the CEB, we will be
happy to assess supply…
(b)… You would notice that the contract manufacturer
is not listed as an ELI certified supplier, however the products they produce
are certified and Philips has independently tested the product under their
application. If you require more details you can contact by e-mail Ms ...
(c) We deal with Philips…We also deal with the
contract manufacturer directly…
An ODM
(original design manufacturer) is a company which designs and manufactures a
product which is specified and eventually branded by another firm for
sale. Such companies allow the brand
firm to produce (either as a supplement or solely) without having to engage in
the organization or running of a factory.
A primary attribute of this business model is that the ODM owns and
designs in-house the products that are branded by the buying firm. This is in contrast to a contract
manufacturer or CM.
The letter of credit
9. The letter of credit was issued by Standard Bank and
notified to APS on 27 September 2010. It
was not suggested that it was not in conformity with the contract. It was described as Irrevocable Transferable
and the Applicable Rules were described as UCP Latest Version. The date and place of expiry were stated to
be “101230 Port Louis Mauritius”. The
date of expiry was thus 30 December 2010. The amount was US$763,725. Partial shipments and transhipment were
allowed. The place of taking in charge
or receipt was given as South Africa and/or Asia and the place of final
destination or delivery was Port Louis, Mauritius. The latest date of shipment was 30 November
2010. The documents required were set
out in detail and the period of presentation was said to be within 15 days
after shipment date but within the validity of the credit. There was no requirement for any certificate
of inspection or similar document to be presented to the bank. The credit was
advised through and negotiated at Mauritius Commercial Bank Ltd (“MCB”) who
were in fact APS’s bankers.
Relevant events before and
at the application on 15 November 2010
10. The goods were manufactured by Sichuan CB Light Co Ltd
(“Sichuan Light”). On 23 September 2010
the MCB provided the CEB with a performance guarantee for APS. In early October there were email exchanges
between APS and the CEB about delivery in which Mr Dookhee of APS gave an
indication of delivery dates and the CEB asked if the delivery could be “sped
up” so that the first container reached them by the end of October. On 18 October MCB notified
Standard Bank that the
letter of credit had been partially transferred to CB Light
to the extent of US$
613,800. On that day Mr Dookhee said by
email that, subject to space, the first container should be leaving within 12
to 14 days and that the CEB’s agent should be able to check the finished goods
“in the southern city of foshan in guangdong province either in xiaolan or
guzhen”. He added that the agent would
need to meet him in either Guangzhou or Shenzhen.
11. On 25 October the CEB submitted a request to Standard Bank for
the letter of credit to be amended with regard to the additional documents to
be submitted by APS, namely (i) a copy of an inspection certificate to be
submitted to the CEB prior to shipment and (ii) a copy of written confirmation
by the CEB that the goods could be released for shipment. Importantly, on 4 November MCB informed
Standard Bank that APS was not agreeable to the amendment sought. The CEB was informed accordingly.
12. In the
meantime, on 28 October Mr Dookhee emailed the CEB under the heading “Warehouse
details for inspection” as follows:
“As I have explained to you on various occasions and
on the telephone yesterday, we contracted the manufacturing to an odm
manufacturer. … The finished product is already ready and
awaiting shipment. It can either be in a
logistics centre at the assembly units either in light city (guzhen) or
xiaolan,
FOSHAN.
DEPENDING WHERE GOODS ARE WHEN WE MEET YOUR INSPECTOR, WE WILL TAKE HIM
THERE TO THE MOST LOGICAL PLACE TO ENSURE THAT HE CAN CARRY A THOROUGH INSPECTION.
I REITERATE THAT OUR MODUS OPERANDI WE MEET AT GARDEN Hotel
and from there we take you for inspection. “
The email gave detailed
information about shipment and said that normally custom clearance would take 2
to 3 days and transit would take 14 to 17 days. Mr Dookhee had also emailed on
25 or 26 October to say that they were ready to ship and to ask the CEB to
liaise with their inspector and ask him to contact him. He added that, if he did not hear by Friday
29 October, he would assume that an inspection was no longer necessary. The CEB replied on 29 October that they would
be “finalising the modalities of the inspection by early next week” and that
they would inform him accordingly.
13. On 4 November the CEB’s UK agents emailed to say that they had
issued inspection instructions to their inspectors in China, namely Shanghai
Inspection Company, and that they had requested their inspection co-ordinator,
Ms Grace Qiang, to contact APS and arrange the inspection. The mail was copied to “grace”. On 9 November Mr Dookhee emailed the CEB’s
agents to say that he had not heard from Ms Qiang and to ask them to forward
her contact details so that he could liaise with her and arrange for the
inspection. On the same day he emailed
Mr Tulloo of the CEB in these terms, putting pressure on them to assist:
“We are currently liaising with your appointed crown
agents in regards of the current order. We have also appointed bureau veritas
and sgs to carry the spectroradiometric analysis on the goods. Our position still remain the same as per
email on the 25th which was sent to the CEB.
In the meantime, can you please ensure that the
shipment dates are amended to reflect your intention and action when the ceb
specifically requested to withold packing and mounting. We have all components
ready and would like to go ahead with the finishing. I hope that we can get the
inspection issues over with your agents.
We will need to finalise parameters regarding
inspection of your odm order.”
On 10 November the CEB
emailed Mr Dookhee saying that he had said during a telephone conversation on 9
November that the manufacturer was no longer Ningo Blunt and asking for the
name and full contact details of the manufacturer, which were essential to them
and their agents.
14. On 11 November the CEB lodged its first application in
Mauritius for an injunction restraining Standard Bank from paying under the
letter of credit. On the next day, 12
November, the CEB sent a fax to APS, with a copy to Standard Bank, referring to
clauses 26.1 and 26.2 of the SCC, and saying that their representative would
contact them shortly for the purposes of “all routine tests to be carried out
at your factory prior to the shipment of the lamps.” Also on 12 November, the CEB wrote to APS
setting out the terms of clauses 26.1 and 26.2 (which are quoted in para 6
above) and adding that their representative would shortly contact APS “for the
purpose of all routine tests to be carried out at your factory prior to
shipping of the lamps”. On 13 November the
goods were shipped on board the M WELLINGTON in Guangzhou by CB Light, although
it has been Mr Dookhee’s evidence throughout that he was unaware that shipment
had taken place.
15. The application lodged on 11 November came before the court on
15 November. The CEB and the then first
respondent, Standard Bank, were represented by counsel and Mr Dookhee was there
in person on behalf of APS, the then second respondent. According to the order signed by the judge,
Mr Dookhee told the court that he did not have a copy of the application but that
he had no objection to an inspection being carried out as per the SCC and that
no shipment would take place unless the inspection was carried out to the
satisfaction of the CEB. On that footing
Standard Bank said that it would not make payment until shipment was effected
and the CEB withdrew its application.
There was no order for costs.
Events before and at the
application on 1 December 2010
16. On 17 November a bill of lading marked ECOTRANS was issued
showing CB Light as the consignor (or shipper) of goods at Ghangzhou on board
the vessel M WELLINGTON on 13 November for discharge in Singapore but with the
place of delivery as Port Louis in Mauritius.
The goods were stated to be consigned to the order of Standard Bank in
Mauritius and the CEB in Mauritius were named as the notify party. On 20 November APS issued an invoice in
respect of the goods.
17. On 22 November an attorney wrote to APS on behalf of the CEB
making a number of allegations which can be summarised in this way. In an email dated 22 February 2010, which
formed part and parcel of the contract dated 3 September 2010, APS had
undertaken to supply bulbs manufactured by Philips. APS had agreed to supply to the CEB the
factory address where the inspection of the bulbs would take place. The CEB
would cause their agent to inspect the goods at the factory duly licensed by
Philips to manufacture the bulbs. APS
had made a commitment to the judge that there would be no shipment prior to
inspection. The CEB would only accept
delivery of bulbs manufactured by Philips and all the bulbs must be labelled
Philips. The letter concluded by saying
that, if it was found during the inspection that the bulbs had not been
manufactured at a factory licensed by Philips or had not been manufactured by Philips,
APS would be in breach of contract. The
attorney added that the CEB reserved their right to take such legal steps as
they might be advised.
18. On 24 November APS provided documents to MCB for presentation
to Standard Bank under the letter of credit.
It appears that the documents were so presented because on 29 November
Standard Bank wrote to the CEB advising them that there were 11 discrepancies
and asking them whether they waived the discrepancies or whether they wanted
the documents to be returned to the negotiating bank, namely MCB. It appears that the CEB did not reply.
19. On 30 November, according to a second bill of lading, entitled
“Ocean Bill of Lading – Negotiable”, the bulbs were loaded on to a vessel named
MALAYSIA EXPRESS at Singapore for discharge in Port Klang in Malaysia. The place of delivery was again described as
Port Louis in Mauritius. It thus appears
that the bulbs were transhipped from the M WELLINGTON at Singapore. The bill of lading named the consignor as
Deutsche Factors and Trade Finance, which suggests that CB Light had discounted
the transferred letter of credit.
20. On 1 December a further application was made in chambers. According to the order made on the same day
it was made in the presence of APS (presumably through Mr Dookhee) and ex parte
as to Standard Bank. It was ordered that
an interim order in the nature of an injunction do issue prohibiting Standard
Bank from making a payment under the letter of credit of US$ 801,911.18 or any
lesser sum to APS. It was stated to be
in force until 10.00 hours on 3 December, when
Standard Bank and APS were
to “show cause, if any, why above interim order should not be made
interlocutory, enlarged, discharged or otherwise dealt with”. The CEB gave an undertaking in damages. On 2 December Standard Bank repeated an
earlier statement it had made on 8 November to the effect that if compliant
documents were presented it would pay under the letter of credit.
The hearing on 3 December
21. At the hearing on 3 December, the CEB and Standard Bank were
legally represented and APS was represented by Mr Dookhee. The following appears from the recitals to
the order of that date. Counsel for the
CEB submitted that Standard Bank could not make payment because there were
certain discrepancies in the documents which had to be sorted out with the
CEB. It is perhaps of note that there is
nothing in the order to suggest that any allegations of fraud were being made,
let alone fraud of which Standard Bank was aware. Mr Dookhee said that he would not retain
counsel. He also told the court that he
was surprised when he found out that the goods had been shipped and that, as
soon as he knew about it, he caused payment to be stopped. He further said that he had asked that the
goods be sent back to the factory for verification and that he had no objection
to Standard Bank withholding payment until the goods had been checked by the
CEB. According to the order, CEB moved
to withdraw the application and the judge discharged the order, with no order
as to costs.
22. In an affirmation made on 11 January 2011 Mr Dookhee said that
the order did not accurately recite what he had said. He contended that what he said was that
inspection at the factory could still be made available and that payment could
await such inspection in that on 3 December the goods were on their way to Port
Klang and could still be turned back. He
added in the affirmation that the CEB did not seem to be interested and did not
contact him for the necessary modification of the shipment date and payment as
stated in his email to the CEB on 9 November, which is quoted in para 13
above. As was submitted on behalf of
APS, it must have been apparent to all concerned that, if the goods were to be
turned round, sent back to China and discharged for inspection, there was the need
for extensions of the latest date of shipment and of the date of expiry of the
letter of credit.
Events before and at
hearings on 21 and 23 December 2010
23. Also on 3 December, at the request of the CEB, MCB recalled the
discrepant documents, which were returned on 6 December. They were remitted back to the CEB on 7
December. On 9 December Standard Bank
wrote to the CEB repeating that, should compliant documents be presented, it
would proceed with payment under the letter of credit. On the same day APS issued a further invoice
in the same amount and Mr Dookhee wrote to the CEB in these terms:
“Please be advised that
despite we have on numerous occasions offered both verification of goods and
modus operandi of the verification for goods ordered under purchase order
number CA/3051, you the CEB has failed to notify us in writing of the identity
of the representative as per clause 4 (a) and further to that you have failed
to provide parameters of inspection despite we have requested such OVER 7 WEEKS
AGO.”
He added that APS had no
alternative other than to claim payment under the letter of credit, that the
goods should be arriving in Mauritius on or about 1 January 2011 and that he
had attached some samples. Those samples
appear to have been received and signed for on 15 December.
24. On 10 December the CEB served a Mise en Demeure, which is a
form of letter before action, on Standard Bank and APS. Among other things it set out the statements
said to have been made on behalf of APS before the court on 15 November, namely
that the goods would not be shipped until verification at the factory to the
satisfaction of the CEB, and complained that those statements had been made
notwithstanding the fact that, as it had learned on 30 November, the goods had
been shipped on 13 November. Moreover,
it was there asserted that, in breach of contract, APS had not allowed any
verification or inspection of the goods and that no payment could or should be
effected under the letter of credit until there had been inspection at the
factory to the CEB’s satisfaction.
25. It further relied upon the statements made on behalf of APS on
3 December that Mr Dookhee was not aware that the goods had been shipped, that
as soon as he learned of that fact he caused payment under the letter of credit
to be stopped, that he had requested the goods to be returned to the factory
for verification and that he had no objection to payment being withheld until
such an inspection had taken place. APS
was called upon forthwith to write to Standard Bank informing it that no such
inspection or verification had been carried out through no fault of the CEB and
that it should not pay until such an inspection had taken place to the CEB’s
satisfaction. Standard Bank was called
upon to confirm within 24 hours that it would not pay save in those same
circumstances.
26. In Standard Bank’s response of 15 December it took issue with
the case against it (including any suggestion that it had given any relevant
undertaking) and reiterated that, should compliant documents be presented on or
before 30 December, it would be bound to pay within 5 banking days. In the meantime, on 14 December MCB presented
what it said were conforming documents to Standard Bank. On 16 December the CEB made a demand under
the performance guarantee asserting that the supplier had defaulted under the
contract.
27. On 17 December Standard Bank communicated a further advice of
discrepancy to CEB together with certain shipping documents. On 20 December Standard Bank sent a
corresponding advice of refusal to MCB, which contested the discrepancy. The
Board is unsure whether this issue was resolved.
28. On 21 December the CEB made a further application to the
court. It sought and obtained an ex
parte interim order restraining Standard Bank from paying under the letter of
credit and an order requiring APS and Standard Bank to show cause why such an
order should not be made interlocutory “pending the main case that will be
lodged shortly”. On the same day the
judge made an order to that effect setting a return date of 23 December. He also required the CEB to give a
crossundertaking in damages, which it seems was to be given to both APS and
Standard Bank. On 23 December the judge
enlarged the injunction until a hearing fixed for 11 January 2011. He noted in the order that APS was
represented by Mr Dookhee who tried to make certain comments but was advised to
seek legal assistance in order to put everything in an affidavit. Counsel for Standard Bank indicated that, as one
would expect, Standard Bank would abide by the decision of the judge and that
he (counsel) would file an affidavit on its behalf. In the event the substantive hearing took
place on 28 January 2011 and judgment was handed down on 28 February 2011.
The fraud alleged against
APS
29. The case for the CEB was summarised in Mr Tulloo’s affirmation
of 21 December 2010. It alleged that the
bid made by APS mentioned that the CFLs would be manufactured by Philips or
under licence by Philips in China. It
further alleged that APS was throughout in breach of the tender documents
because it had not allowed and/or authorised the CEB to inspect and verify the
660,000 CFLs at the place of manufacture in China. It is perhaps notable that, as submitted on
behalf of APS, although the affirmation was made in support of an ex parte
application, it did not exhibit or make any reference to the various email
exchanges and other communications relating to inspection which the Board has
described above. APS was also said to be
in breach of the contract and of an undertaking given to the court by Mr
Dookhee on 15 November that he had no objection to an inspection being carried
out and that no shipment would take place unless an inspection was carried out
to the satisfaction of the CEB because the true position was that the goods had
already been shipped on 13 November 2010.
Mr Tulloo further complained in para 24 that, contrary to the statements
recorded in the orders of 15 November and 3 December, the goods were shipped
from Singapore instead of China on 30 November 2010, whereas Mr Dookhee had
stated on 3 December 2010 that he would cause the goods to be shipped back to
China for inspection by the CEB.
Moreover, according to the second bill of lading, the goods were loaded
at Singapore and the consignor was stated to be Deutsche Factors and Trade
Finance, which was unknown to the CEB. Mr Tulloo asserted that the consignor
ought to have been a consignor from China which had manufactured the 660,000
units.
30. Based on those assertions, in para 25 Mr Tulloo sought to draw
the inference that APS was acting fraudulently in order to defraud the CEB of
US$763,725 without any consideration.
APS should not be entitled to claim any payment because, as Mr Tulloo
put it in para 26,
“[APS] is not supplying the
goods as agreed (ie bulbs manufactured by Philips or manufactured under licence
by Philips) and has not allowed the [CEB] to inspect and verify the bulbs at
the place of manufacture. [APS] has, twice, breached the undertaking given by
it in Court.”
Mr Dookhee’s affirmation
31. Mr Dookhee made an affirmation on 11 January 2011 in response
to that of Mr Tulloo. He exhibited the
exchanges between the parties referred to above which show the attempts made by
APS to arrange for the CEB to inspect the goods. Mr Dookhee admitted that on 15 November he
had told that court that APS had no objection to a verification of the goods
being carried out by or on behalf of the CEB as per the SCC in the contract and
that the goods would not be shipped until that been done. However, he said that when he made that
statement he did not know that the goods had already been shipped. It should be noted in this regard that the
first bill of lading was dated 17 November, which was of course after the hearing
on 15 November. Moreover, APS was not
the shipper.
32. There is an issue as to what Mr Dookhee told the court on 3
December. There is no transcript of the
hearing and there is no evidence as to how the recitals came into the order of
that date. Mr Dookhee admitted that on 3
December he told the court that inspection at the factory could still be made
available and that payment could await such inspection in as much as the goods
were then on their way to
Malaysia and could still
turn back. He did not however accept
that he had said
that he had already caused
payment to be stopped or that he had asked that the goods be sent back to the
factory for verification. By way of
explanation of what happened thereafter, he added that the CEB did not seem to
be interested and did not contact him for the necessary modification of the
shipment date and payment date as stated in his email to Mr Tulloo on 9
November referred to in para 13 above.
In his affirmation Mr Dookhee then described the subsequent presentation
of the documents and denied any wrongdoing.
The judgment at first
instance
33. The judge correctly recognised at page 24, line 22 that it was
common ground that the court will not intervene to stop payment under an
irrevocable letter of credit because, as he put it, that will have a far
reaching effect on the international trade of the country. That is a reflection of the important
principle stated in a number of cases that, subject to the fraud exception, the
paying bank must pay under a letter of credit provided only that the documents
presented to it conform to the formal requirements of the letter of
credit. The bank is not concerned with
any underlying dispute between the parties.
That principle is underlined in this case by the fact that any such
dispute is subject to the arbitration clause in the contract.
34. The judge referred to a number of cases including Edward Owen
Engineering Ltd v Barclays Bank International Ltd [1978] QB 159; Power Curber
International Ltd v National Bank of Kuwait SAK [1981] 1 WLR 1233; Bolivinter
Oil SA v Chase Manhattan Bank NA [1984] 1 WLR 393; and United City Merchants
(Investments) Ltd v Royal Bank of Canada (also known as The American Accord)
[1983] 1 AC 168. So far as the
underlying principle is concerned, it is sufficient to refer to only two
sources among many. The first is this
sentence from judgment of Sir John Donaldson MR in Bolivinter Oil SA v Chase
Manhattan Bank NA at p 393, which the judge quoted and underlined at p 26 line
20:
“The unique value of such a letter, bond or guarantee
is that the beneficiary can be completely satisfied that whatever disputes may
thereafter arise between him and the bank's customer in relation to the
performance or indeed existence of the underlying contract, the bank is
personally undertaking to pay him provided that the specified conditions are
met.”
The second source is the
judgment of Lord Denning MR in the Edward Owen case, where he stated the
general principle at p 169 and added his approval of what has now become the
oft quoted statement of Kerr J in RD Harbottle (Mercantile) Ltd v National
Westminster Bank [1978] QB 146 at p 155 that irrevocable obligations assumed by
banks are the life-blood of international commerce.
35. The judge therefore correctly recognised that an injunction
should only be granted to restrain a bank from paying under a letter of credit
where the fraud exception applies and the bank is aware of the fraud. He referred to a number of the relevant cases
in this field. However, he did not state
the relevant test in consistent terms throughout his judgment. For example, on page 26 at line 45 he quoted
this further passage from the judgment of Sir John Donaldson MR in Bolivinter,
also at p 393:
“The wholly exceptional case
where an injunction may be granted is where it is proved that the bank knows
that any demand for payment already made or which may thereafter be made will
clearly be fraudulent. But the evidence must be clear, both as to the fact of fraud
and as to the bank 's knowledge. It would certainly not normally be sufficient
that this rests upon the uncorroborated statement of the customer, for
irreparable damage can be done to a bank's credit in the relatively brief time
which must elapse between the granting of such an injunction and an application
by the bank to have it discharged.”
The judge underlined the
first sentence of that passage but not the rest. At p 28 line 32 the judge quoted the whole
passage in support of the proposition that knowledge on the part of the bank as
to the fraud must be established by strong corroborative evidence. He also cited United Trading Corp SA v Allied
Arab Bank Ltd [1985] 2 Lloyds' Rep 554 at 561 to that effect. After referring to other cases, the judge
concluded at p 29 line 38 that it was clear that the bank is not obliged to
investigate when there is an allegation of fraud. It is for the client to do so by producing
compelling evidence that fraud has been committed.
36. The judge then referred to the question whether a man who makes
a statement without care as to its truth or falsity commits a fraud and
concluded that he does at p 30 line 10.
He concluded at line 19 that it was clear that the court would not issue
an injunction to restrain or prohibit payment under an irrevocable letter of
credit if all the conditions had been complied with and that it is only in the
case
“where there is fraud on the
part of the beneficiary which is to the knowledge of the bank that the court
will interfere.”
37. However, as the Board reads his judgment, the judge ultimately
reached his conclusion by reference to a different test which he said was based
upon the decision of Kerr J in Harbottle.
The judge put it thus on p 33 at line 40:
“In the light of the principles laid down in
[Harbottle] I find that the applicant has raised a serious prima facie arguable
case that there might be an attempt to defraud it which must be left to the
competent court or to the arbitrator as provided for in the contract to deal with
the issue. The balance of convenience clearly tilts heavily in favour of the
applicant as [APS] is debarred to claim the amount until all the disputes had
been cleared on the maxim of ex turpi causa non oritur actio. As regards any damage, if any, which [APS]
considered it had suffered, the applicant had given an undertaking.”
He therefore converted the interim order made on 21
December 2010 into (as he put it) an interlocutory order “pending the decision
of the main case to be dealt with, most certainly, according to the contract,
by the arbitrator”.
38. It appears to the Board that the judge decided the application
on the basis that it was an interlocutory application, that it was sufficient
for the CEB to establish an arguable case (or, as he put it, a serious prima
facie arguable case) and that it could properly be disposed of on the balance
of convenience. The Board will return to
the correctness or otherwise of this approach below.
39. The conclusions of fact reached by the judge seem to the Board
to be divided into two parts, those relating to the question whether the CEB
was entitled to relief arising out of the presentation of the documents on 14
December and the relevance of the misstatements said to have been made on
behalf of APS to the court at one or more of the hearings in November and
December. As the Board sees it, there
can be no question of Standard Bank being required to pay as a result of the
earlier presentation, when there were said to be 11 discrepancies.
40. In making his findings of fact, the judge set out a short
summary of the contract on p 30. He
correctly observed that it was important to identify the conditions stated in
the letter of credit. He was struck by
four points: (1) that among the documents required by the bank were the
conditions of sale which could only be found in the contract; (2) that the
period of presentation was within 15 days after shipment but within the
validity of the credit; (3) that the validity expired on 30 December 2010 but
that, more importantly, the latest date for shipment was 30 November; and (4)
that the goods were to be imported from China but there was no bill of lading
which showed that the goods had been loaded in China.
41. The judge observed that it was not in dispute that APS presented
the documents immediately after the goods were shipped on 13 November (although
the documents were in fact presented to Standard Bank on or shortly after 24
November) and that Standard
Bank had notified the CEB of the presentation and
of the discrepancies that
had been found. He further concluded
that Standard Bank became aware of the fact that no shipment could be effected
without verification of the goods at the place of manufacture in China at the
latest at the hearing on 15 November, when the statement was made on behalf of
APS. He added that it could not be
gainsaid that shipment could not be effected without prior verification of the
goods by the CEB in China. He held that
the application for an injunction on 1 December was shortly after the CEB
became aware that the goods had been shipped on 13 November. He further held that at the inter partes
hearing on 3 December the representative of APS, who was of course Mr Dookhee,
boldly made the statements set out in the recitals to the order. As stated in para 21 above, they were that
that he was surprised when he found out that the goods had been shipped, that
as soon as he knew about it, he caused payment to be stopped, that he had asked
that the goods be sent back to the factory for verification and that he had no
objection to Standard Bank withholding payment until the goods had been checked
by the CEB.
42. It is plain that the judge took a dim view of Mr Dookhee
because he said that his acts were contrary to those bold statements. The judge noted that APS had been advised to
retain the services of legal advisers.
As the Board reads the judgment, the judge did not reach a final
conclusion as to the true position. He
did however hold at p 31 line 34 that in all the circumstances it was certainly
the duty of Standard Bank to ascertain that verification had been carried out
before shipment. He did not explain the
basis upon which he reached that conclusion.
43. The Board agrees with counsel for APS that the following
passages (at pp 31 to 33) contain the ratio decidendi of the judge’s judgment:
“I am certainly not concerned with the specification
of the goods whether they complied with the agreement or not, … What matters …
is that no shipment of the goods would be effected until the goods had been
verified by the applicant at the factory in China as per the terms of the
agreement. In the circumstances, it was not open to [Standard Bank] to pay the
irrevocable letter of credit as the bank is aware that the terms and conditions
of the contract namely verification of the goods, which had been mentioned in
the contract, the latter is a document which must be produced according to the
irrevocable letter of credit, had not been complied with. It had also not
received written confirmation from [the CEB]. If there is no verification, it
stands to reason that the contract had not been complied with and consequently,
there could be no shipment.
It must also be borne in mind that [Standard Bank] is
saying that the request for payment was made on the strength of the document
showing that shipment of the goods had been effected on the 30th November 2010.
It must be clear to [Standard Bank] that the document in question could not be
relied upon in view of the statements made by the representative of [APS] during
the first two applications that there would be no shipment until there had been
verification. [Standard Bank] was also given notice by [the CEB], which it
could not ignore in the circumstances of the case, that confirmation would be
given whether verification would be effected or not.
I do not understand why no verification could be
carried out as provided for in the contract and why [APS] is in a hurry to
claim payment despite the undertaking given by its representative before me
which it knew was a special condition of the contract and which had not been
complied with. There is no evidence that [APS] had put [CEB] 'en demeure' to
come to verify the goods at the factory and that the applicant had failed to
comply with the notice. It seems that it was the applicant who through its
attorney at law on the 22nd November 2010 was prepared to cause its agent to
inspect the goods at the factory.
…
What [APS] is trying to do
in the circumstances is certainly deceit and fraudulent in the words of Cotton
J alluded to above and which is to the knowledge of [Standard Bank] and which
it could not feign not to be aware in the light of the two applications coupled
with the notice given to it by [the CEB] and in the light of the various
authorities referred to above.
[APS]’ representative had
shown his utter bad faith in blatantly ignoring the undertaking made before me
and trying to claim payment without complying with the terms of the irrevocable
letter of credit. Even before any verification of the goods at the factory, the
goods were allegedly loaded on the 30th November 2010 in Singapore. Obviously,
that was done to beat the deadline as provided in the irrevocable letter of
credit.”
44. The reference to Cotton J is a reference to a statement by
Cotton LJ which was approved by Lord Bramwell in Derry v Peek (1889) 14 App Cas
337, 350 to the effect that “the law is ‘that where a man makes a statement to
be acted on by others which is false, and which is known by him to be false, or
is made by him recklessly, or without care whether it is true or false, that is
without any reasonable ground for believing it to be true’, he is liable to an
action for deceit.”
The judge also referred in
passing to what he described as other matters which had been raised by the
applicant regarding the bill of lading and the marine cargo policy which
appeared to be disturbing but which he need not consider but left to the
arbitrator to decide.
45. The judge then said that the case before him was not whether
the bulbs must be of Philips make or not.
That would be a contractual question not relevant to the question
whether Standard Bank must pay under the letter of credit. He continued at p 33:
“Here, the question is that
there should be verification and inspection of the goods at the factory by the
applicant before the goods could be shipped. It is to the knowledge of
[Standard Bank] that there could not be shipment until verification and
inspection had been carried out. It is a term of the contract which is
mentioned in the irrevocable letter of credit and the conditions of sale must
be produced as mentioned in the irrevocable letter of credit. The applicant had
notified [Standard Bank] that it would send confirmation whether verification
had been effected.
The question is whether [APS]
had fraudulently loaded the goods on board the ship without giving the
applicant an opportunity to verify and inspect. It would have been a different
matter had [APS] put the applicant “en demeure” to come, verify and inspect the
goods at the factory and the applicant failed to attend. Nothing would have
prevented [APS] to load and ship the goods then. [Standard Bank] cannot in the circumstances
of the case be heard to be saying that if it received all the required
documents, it would pay. Here an issue
of fraud had been raised and [Standard Bank] is fully conscious that no
shipment can be effected until verification and inspection. The date of
shipment will be an issue (vide The American Accord Case) which [Standard Bank]
had to check since it would only pay within 15 days of shipment on presentation
of all relevant documents.”
46. On the basis of those conclusions of fact the judge held that,
in the light of the principles in the Harbottle case, the CEB had raised “a
serious prima facie arguable case that there might be an attempt to defraud it
which must be left to the competent court or to the arbitrator to determine as
provided for in the contract”. He added
that the balance of convenience tilted heavily in favour of the CEB “as [APS]
is debarred to claim the amount until all disputes had been cleared on the
maxim of ex turpi causa non oritur actio.”
He added that if APS suffered any damage it would be protected by the
undertaking in damages.
Decision of the Court of
Appeal
47. APS appealed to the Supreme Court sitting as a Court of
Appeal. As stated above, the appeal was
dismissed. The Court of Appeal affirmed
the decision and reasoning of the judge, relying in particular upon what Mr
Dookhee said to the judge but went somewhat further. It held (which the judge expressly did not)
that the contract required that “the lamps would be manufactured by Philips or
under licence by Philips in
the Republic of China” and that clarification no 2 (referred to above)
contained “misleading and false representations”.
48. The Court of Appeal expressed itself in strong terms. As to the submissions made on behalf of APS
on the fraud exception, it said at para 14:
“The stand of the appellant
as expounded by its Counsel on appeal that it is not the role of the bank to go
beyond the ILC and to delve into the terms of the Contract before honouring the
ILC is correct only in so far as it is the run of the mill case - not when it
has been made a party in Court proceedings, undertakings have been given by the
appellant and ought to have been complied with by the latter.”
The court then accurately
described the general principle in the cases, namely that the unique value of a
letter of credit is that the beneficiary can be completely satisfied that,
whatever disputes may thereafter arise between him and the bank's customer in
relation to the performance or indeed existence of the underlying contract, the
bank is personally undertaking to pay him provided that the specified
conditions are met. It added that the
exceptional case where an injunction to stop payment may be granted is where it
is proved that the bank knows that any demand for payment already made or which
may thereafter be made will be clearly fraudulent.
49. However, the court concluded at para 15 that on the affidavit
evidence APS should have been estopped from applying for payment under the
letter of credit
“in view of (a) the
commitment it took in the presence of the Bank not to claim payment under the
ILC unless verification of the lamps had taken place at the factory to the
satisfaction of CEB before the shipment; and (b) its shiftiness to name the
factory where the lamps were to be manufactured and its inability to arrange
for inspection at the factory before shipment.”
50. In paras 23 to 25 it dismissed the submissions of APS on the
terms of the contract and more generally in strong language as follows:
“23. The appellant denied that it had a contractual
obligation to supply Philips lamps or lamps manufactured under the licence of
Philips and the stand taken before us at the hearing that the appellant's
representations were mere “trade puffs" appear to us to be as base as they
are shameless.
The apparent deceit to pass off a product which is
different from the one it had undertaken to supply was canvassed before the
learned Judge in Chambers and his decision cannot be challenged.
24. Considering
the callous way in which the appellant's director had acted throughout the
execution of the contract, knowingly making gross misrepresentations to obtain
the tender and then reneging the undertakings given in Court during the various
applications, one can only conclude that the case had been amply made out that
the attempt to obtain payment was fraudulent. It is patent that Mr Dookhee had
no intention of complying with his undertaking to supply Philips lamps or lamps
manufactured under licence from Philips. He was bent on hoodwinking the CEB by
giving flimsy undertakings in Court to foster his plan to make an abuse of the
normal payment procedures and advantages of an ILC with clear intent to defraud
the CEB.
25. There is
no merit in this appeal which is dismissed with costs”
Discussion
51. Three grounds of appeal are advanced on behalf of APS as
follows. (1) Whatever test is applied,
there is insufficient evidence of fraud to establish the fraud exception so as
to justify the grant of an injunction against Standard Bank. (2) The judge imposed too low a test. (3) In any event the balance of convenience
did not, and does not, justify an interlocutory injunction. It is convenient to consider first the
correct test (ground (2), secondly the evidence of fraud (ground (1) and
thirdly the balance of convenience (ground (3).
The test
52. The judge’s approach to the test is set out at paras 33 to 38
above. As there stated the judge held
that the CEB had raised “a serious prima facie arguable case that there might
be an attempt to defraud”. He held that
the issue of fraud must ultimately be determined by the court or arbitrator as
provided in the contract (here the arbitrator).
His decision to grant the injunction was based upon the application of
the above test on the merits and his conclusion on the balance of convenience
(discussed below). The Board does not
accept the test formulated by the judge.
53. The courts have adopted different tests in different
circumstances. In American Cyanamid Co v
Ethicon Ltd [1975] AC 396 the House of Lords held that in the ordinary case, in
order to obtain an interlocutory injunction, the claimant does not have to show
that he will probably succeed, or that he has a prima facie case
or a strong prima facie
case. It is sufficient to show that the
claim is not frivolous or vexatious or, in other words, that there is a serious
issue to be tried: see per Lord Diplock, with whom the other members of the
House agreed, at p 407G. The remaining
question is whether the balance of convenience justifies the grant of an
injunction, having regard, among other things, to the cross-undertaking in
damages.
54. The cases show that that is not the test in the case of a
letter of credit. The test has been
variously described. In Bolivinter at p
393 in the passage quoted at para 35 above Sir John Donaldson MR said that an
injunction may be granted where it is proved that the bank knows that any
demand made will clearly be fraudulent.
It is evident that he was considering the position at the interlocutory
stage because he drew attention to the irreparable damage that can be done to a
bank’s credit in the relatively brief time between the granting of such an
injunction and the time when it can be discharged. The judge in this case recognised (as stated
at para 35 above) that knowledge on the part of the bank must be established by
strong corroborative evidence.
55. Other expressions of the test in the cases include the
following. In United Trading at p 561
Ackner LJ identified the question as whether the plaintiffs had established
that it is seriously arguable that, on the material available, “the only
realistic inference is that [the beneficiary] could not honestly have believed in the validity of
its demands on the performance bonds.”
See also, to the same effect, Group Josi Re v Walbrook Insurance Co Ltd
[1996] 1 WLR 1152, per Staughton LJ at p 1160, where he stated Ackner LJ’s
test. He then referred to Lord Diplock’s
statement of the general principle in the United City Merchants case at p 183
and, in particular, to Lord Diplock’s reference to the only exception to the bank’s
obligation to pay against conforming documents:
“that is, where the seller,
for the purpose of drawing on the credit, fraudulently presents to the
confirming bank documents that contain, expressly or by implication, material
representations of fact that to his knowledge are untrue.”
That might suggest a
stricter test than that stated by Ackner LJ but Staughton LJ added at p 1161
that, when that principle is applied to an interlocutory application, the bank
is bound to pay unless the demand of the beneficiary is “clearly fraudulent”. He relied upon the Edward Owen case.
56. Staughton LJ however concluded that the right course on an
interlocutory application was to adopt Ackner LJ’s test. He added that he followed the view of Lloyd
LJ in Dong Jin Metal Co Ltd v Raymet Ltd (unreported), 13 July 1993,
Court of Appeal (Civil
Division) Transcript No 945 of 1993, that it does not make much difference
whether one says that the letter of credit cases are special cases within the
American Cyanamid guidelines, because of the special factors which apply in
such cases, or whether one says that such cases fall outside the guidelines and
that he preferred the former view.
57. In a detailed and impressive analysis of the law in
Czarnikow-Rionda Sugar
Trading Inc v Standard Bank
London Ltd [1999] 2 Lloyd’s Rep 187 Rix J included the following:
“(4) An additional dimension
of complexity is superimposed by the fact that a final decision on the
beneficiary's alleged fraud cannot be reached at a merely pre-trial hearing. Of
course, the fraud exception is framed in such terms, requiring the fraud to be
clear and to come to the timely knowledge of the bank, that in one sense there
ought not to be a difference between a pre-trial application and the final
trial. But life and the law are not perhaps as simple as that, and the
difference between the tests formulated for the pre-trial stage and for final
trial emphasize the difficulty. However, the fact that the claimant gets the
benefit of a lower standard of proof for the purposes of a pre-trial hearing,
places on the Court, as I believe the cases demonstrate, an additional
requirement to be careful in its discretion not to upset what is in effect a
strong presumption in favour of the fulfilment of the independent banking
commitments.” (p 202)
58. In Solo Industries UK Ltd v Canara Bank [2001] 1 WLR 1800,
Mance LJ said this at paras 31 and 32:
“31 … If instruments such as
letters of credit and performance bonds are to be treated as cash, they must be
paid as cash by banks to beneficiaries. The courts in the Harbottle and Edward
Owen cases emphasised this, and, in my view, set a higher standard than ‘a real
prospect of success’ in relation to all these situations. Short of ‘established
fraud’, a bank will not normally be allowed to raise any defence or set-off
based on alleged impropriety affecting the demand.
32. It may be suggested that the reformulation
of the test in the United Trading case … lowers the standard. The court
expressed the test at the interlocutory stage, as being (under the old rules)
whether ‘it is seriously arguable that, on the material available, the only
realistic inference is that [the beneficiary] could not honestly have believed
in the validity of its demands on the performance bonds’. In that
reformulation, the first four words would now have to be replaced by the words
‘there is a real prospect’. I have some reservations about the reformulation,
and note what Rix J said in the Czarnikow-Rionda case … point 4. The courts in
the Harbottle and Edward Owen cases were concerned with the interlocutory
stage. The test that they stated was undiluted by any reference to ‘arguable
case’. The defence that they and later authorities identify, of established
fraud known to the bank, is, by its nature, one which, if it is good at all,
must be capable of being established with clarity at the interlocutory stage.
If and so far as that defence is limited to the time when demand was or payment
should have been made, but the court will still refuse judgment if by the time
of judgment fraud is established, again there would seem to be little room for
considering whether there is an ‘arguable case’ or ‘real prospect’ of
establishing fraud. On any view, as Rix J observed, the court should be careful
not to allow too extensive a dilution of the presumption in favour of the
fulfilment of independent banking commitments. The introduction of the balancing
concept of ‘the only realistic inference’ and the actual conclusion on the
facts in the United Trading case suggest that the court there also had this
consideration in mind.”
59. The Board agrees with the reasoning of Rix J and Mance LJ in
those passages. It recognises that the
test cannot be quite the same as at a trial and that the test at the
interlocutory stage can properly be described as Ackner LJ described it, namely
whether it is seriously arguable that, on the material available, “the only
realistic inference is that [the beneficiary] could not honestly have believed
in the validity of its demands on the performance bonds” and that the bank was
aware of that fact. In the view of the
Board the expression “seriously arguable” is intended to be a significantly
more stringent test than good arguable case, let alone serious issue to be
tried. As Mance LJ put it, a case of
established fraud known to the bank, is, by its nature, one which, if it is good
at all, must be capable of being established with clarity at the interlocutory
stage. In summary, the Board concludes
that it must be clearly established at the interlocutory stage that the only
realistic inference is (a) that the beneficiary could not honestly have
believed in the validity of its demands under the letter of credit and (b) that
the bank was aware of the fraud.
Evidence of fraud.
60. The relevant presentation of documents under the letter of
credit was the second presentation, which was on 14 December 2010. There is no suggestion that any of the
documents presented to Standard Bank were forgeries or that any of them
contained, to the knowledge of APS, any material express
misrepresentation. Nor is it suggested
that, in presenting the documents, APS made any implied misrepresentation,
whether innocently, or knowingly and dishonestly.
61. So far as statements in the documents presented are relied
upon, as stated in para 29 above, Mr Tulloo complained that the goods were
shipped in Singapore instead of China and that the consignor was named as
Deutsche Factors and Trade Finance, which was unknown to the CEB and was not in
China. However, the Board accepts the
submission made on behalf of APS that the second bill of lading did not contain
any misrepresentation. It showed the
port of loading as Singapore, which was within the terms of the letter of
credit, which (as stated in para 9 above) provided for the place of taking in
charge or delivery as South Africa and/or Asia and expressly permitted
transhipment. The goods were shipped in
China and transhipped in Singapore, both of which were permissible under the
terms of the letter of credit. As to the
identity of the consignor, no misrepresentation is alleged. Moreover the letter of credit contained no
requirement as to the identity of the consignor as opposed to the consignee
and, in any event, it seems that CB Light had discounted the transferred letter
of credit.
62. Mr Tulloo further states in his second affirmation of 18
January 2011 that the CEB verily believed that the vessel M WELLINGTON did not
originate from China and therefore that the first bill of lading may not be
accurate. However, there is no evidence
which supports that belief and Mr Dookhee said in his affirmation that it was
well known in the shipping industry that the M WELLINGTON transported goods
from China. Finally, there is an issue
as to whether container numbers were not set out in either bill of lading. However, that does not appear to be correct
and, in any event, there was no such requirement in the letter of credit.
63. It appears to the Board that the judge’s decision was not so
much based upon the documents presented to Standard Bank as upon the view he
took of the representations made to the court by Mr Dookhee. In particular, as stated at para 15 above,
the order signed by the judge shows that on 15 November Mr Dookhee said that he
had no objection to an inspection being carried out in accordance with the
terms of the contract and that no shipment would take place unless the inspection
was carried out to the satisfaction of the CEB.
The judge took a dim view of that statement because it later transpired
that the ship had already sailed on 13 November with the goods on board. Mr Dookhee has maintained throughout that he
did not know that shipment had already taken place. Although the judge was sceptical (to put it
no higher), there is no evidence that Mr Dookhee was aware that the goods had
already been already shipped. It seems
most unlikely that he knew because, if he did, there seems no reason why he
should promise that no shipment would take place until after a satisfactory
inspection. Put another way, it is
surely much more likely than not that the statement that there would be no
shipment unless and until an inspection of the goods had been carried out was
made on the premise that the goods had not yet been shipped.
64. The evidence set out at paras 10 to 13 above shows that Mr
Dookhee had spent a good deal of time and effort into trying to arrange a time
and place for inspection without any very satisfactory response from the
CEB. Moreover, there was no requirement
in the letter of credit that it was APS which was to ship the goods; so it is
far from incredible that Mr Dookhee did not know that shipment had taken place,
especially since the first bill of lading was dated 17 November, which was two
days after the hearing before the judge on 15 November.
65. The next stage is discussed at para 16 to 20 above. As just stated, the goods were shipped on 13
November and the first bill of lading was issued on 17 November. Then on 22 November the CEB made its first
allegations against APS as set out in para 17 above. They included allegations of breach of
contract. An ex parte order was made on
1 December as stated at para 20 above and events at the hearing on 3 December
are described at para 21. No allegations
of fraud were made. The application was
withdrawn because of discrepancies in the documents. However, Mr Dookhee told the judge that he
was surprised when he found out that the goods had been shipped and that, as
soon as he knew about it, he caused payment to be stopped. According to the recital to the order as
drawn up he said that he had asked that the goods be sent back to the factory
for verification and that he had no objection to Standard Bank withholding
payment until the goods had been checked by the CEB.
66. As set out in paras 22 and 31, Mr Dookhee contended that the
recital was not accurate and that what he said was that inspection at the
factory could still be made available and that payment could await such
inspection in that on 3 December the goods were on their way to Port Klang and
could still be turned back. He added
that the CEB did not however seem to be interested and did not contact him for
the necessary modification of the shipment date and payment as stated in his
email to the CEB on 9 November, which is quoted in para 13 above. As the Board indicated in para 22, it accepts
the submission made on behalf of APS that it must have been apparent to all
concerned that, if the goods were to be turned round, sent back to China and
discharged for inspection, the need for an extension, both of the latest date
for shipment and of the date of expiry of the letter of credit, would have been
clear to all concerned. Moreover, the
complaint made by Mr Dookhee in a message to the CEB on 9 December that the CEB
had not co-operated in an inspection of the goods for over seven weeks seems to
the Board to have been justified in the light of the exchanges between APS and
the CEB, which are set out in detail above but which are not referred to by
either the judge or the Court of Appeal.
67. There followed the Mise en Demeure described in para 24 in
which the CEB complained that APS had not allowed any verification or
inspection of the goods
and asserted (among other
things) that no payment should be made until there had been an inspection at
the factory to the CEB’s satisfaction.
68. As appears in para 29 Mr Tulloo relied upon the failure of APS
to supply bulbs manufactured by or under licence by Philips and its failure to
allow the CEB to inspect and verify the bulbs at the place of manufacture. APS denies that it was in breach of contract
in either of those respects and blames the CEB for failing to co-operate in
setting up an inspection of the goods.
For present purposes the difficulty with those allegations is that they
are allegations of breach of contract and thus matters for arbitration and irrelevant
to the liability of Standard Bank under the letter of credit. In so far as the judge relied upon them he
erred in principle. The judge stressed
on more than one occasion that what mattered was that no shipment was to be
effected until the goods had been verified by the CEB at the relevant
factory. Moreover he held that Standard
Bank knew that that was the position and could not properly pay under the
letter of credit. However, as the Board
reads the judgment, the judge placed considerable weight on what Mr Dookhee
said to him (and to Standard Bank) in court.
Leaving that on one side, there is, in the opinion of the Board no
possible basis upon which the fraud exception could apply, whatever the test.
69. The same is true of the Court of Appeal. It went further than the judge. So, for example, in para 24 (quoted in para
50 above) it apparently concluded that APS through Mr Dookhee acted
fraudulently throughout, knowingly making gross representations to obtain the
tender. It added that it was patent that
he had no intention of complying with his undertaking to supply Philips lamps
or lamps manufactured under licence from Philips. In the opinion of the Board, in so far as
those conclusions depend upon an analysis of the true contractual position
between the CEB and APS, they cannot form a proper basis for the grant of an
injunction against Standard Bank.
70. It is striking that neither the judge not the Court of Appeal
considered whether Standard Bank agreed to a variation of the letter of
credit. In order to be valid, such a
variation would have to be agreed by Standard Bank. The bank relies upon articles 4 and 10 of the
relevant UCP, which is UCP 600. Article
4a provides:
“A credit by its nature is a
separate transaction from the sale or other contract on which it may be
based. Banks are in no way concerned
with or bound by such contract, even if any reference whatsoever to it is
included in the credit. Consequently, the undertaking of a bank to honour, to
negotiate or to fulfil any other obligation under the credit is not subject to
claims or defences by the applicant resulting from its relationships with the
issuing bank or the beneficiary.”
Article 10a provides that,
subject to an irrelevant exception, a credit can neither be amended nor
cancelled without the agreement of the issuing bank, the confirming bank, if
any, and the beneficiary. Thus if,
contrary to the case for APS, APS and the CEB had at any stage agreed to a
variation of the terms of the contract, in order to be effective against
Standard Bank, the bank would have had to agree to any variation of the terms
of the letter of credit.
71. There is no evidence that Standard Bank agreed to any variation
of the terms of the letter of credit. On
the contrary, as stated in para 11 above, when the CEB submitted a request to
Standard Bank for the letter of credit to be amended with regard to the
additional documents to be submitted by APS, namely (i) a copy of an inspection
certificate to be submitted to the CEB prior to shipment and (ii) a copy of
written confirmation by the CEB that the goods could be released for shipment,
APS declined to agree and on 4 November MCB informed Standard Bank that APS was
not agreeable to the amendment sought.
The CEB was informed accordingly.
72. Whatever Mr Dookhee said to the judge, even if he promised to
do something outside the terms of the contract, there is no evidence that
Standard Bank agreed to any amendment of the letter of credit as a result. This is important because it appears to the
Board that, in the case of both the judge and the Court of Appeal, the
underlying basis for their conclusions was, not so much that APS was in breach
of contract, but that it dishonestly gave undertakings to the court which it
had no intention of honouring. This was
no doubt based on the evidence of Mr Tulloo referred to in para 29 above that
APS twice breached undertakings given to the court. Even if there were some force in this case as
against APS, it is of no assistance to the CEB in this appeal unless Standard
Bank either agreed a relevant variation of the letter of credit or knew that
APS was acting fraudulently. There is no
evidence of any such agreement and, in the opinion of the Board,
notwithstanding the views expressed by the judge and the Court of Appeal, there
is no evidence that Standard Bank knew that APS was acting fraudulently.
73. The Board accepts the submission made on behalf of Standard
Bank that there was no allegation of fraud in the Mise en Demeure and that it
was not put on notice of any such fraud.
It was aware only of a contractual dispute between APS and the CEB that the lamps were shipped
without verification that they complied with the contract, which was a dispute
with which the bank was not concerned.
Standard Bank has throughout taken the reasonable stance that, subject
to the injunction it was ready to pay under the letter of credit when compliant
documents were presented to it.
74. The central theme running through the parts of the judgment
quoted above is that the judge considered that no shipment of the goods could
be effected until they had been verified by or on behalf of the CEB at the
factory in China in accordance with the terms of the contract and that Standard
Bank was aware of
the position because it was
aware of the terms of the contract and because of the statements made by Mr
Dookhee to the court. However, as stated
above, the judge’s approach was flawed.
He did not refer to the exchanges relating to inspection set out
above. Moreover he did not apparently
consider whether Mr Dookhee might be telling the truth when he said on 15
November that he was not initially aware that the goods had been shipped on 13
November.
75. As to the hearing on 3 December, the Board does not think that
the remarks attributed to Mr Dookhee provide any real assistance to the CEB in
this context. Mr Dookee disputed the
account as attributed to him and the account may not be accurate. His account is consistent with the point he
made that when he said that inspection at the factory could still be made
available, that was on the basis that the vessel would turn back and that there
would be agreed extensions of the letter of credit. Moreover Standard Bank did not perceive that
the events of 3 December had somehow altered its obligations under the letter
of credit. As stated at para 26 above,
in its response to the Mise en Demeure it took issue with the case against it,
including any suggestion that it had given any such undertaking. In any event the issues between the CEB and
APS referred to above remain matters for arbitration even on the hypothesis
that the events of 15 November and 3 December were of some relevance. There is certainly no basis upon which it
could be held that any variation of the letter of credit could be inferred from
those events.
76. In all the circumstances the Board reaches a different
conclusion from the judge. As to the
Court of Appeal, it too rested its decision in part upon the position under the
contract between the CEB and APS, which is not permissible. As appears at para 48 above, the Court of
Appeal accepted the general principle but added that it only applies in a run
of the mill case:
“not when it has been made a
party in Court proceedings, undertakings have been given by the appellant and
ought to have been complied with by the latter.”
The Board does not accept
that general conclusion or its application to the facts as quoted in para 49,
which essentially gives the same reason as the judge discussed above. Further the reasons given in the Court of
Appeal’s paras 23 to 25 quoted in para 50 above are unsound. Para 23 again relates to a contractual issue
and para 24 contains an exaggeration which is not justified on the facts.
77. In all these circumstances, the Board concludes that, whatever
test is applied, neither the judge nor the Court of Appeal was entitled to
reach the conclusion that the fraud exception was satisfied, in the case of
either APS or Standard Bank.
Balance of convenience
78. As stated in para 46 above, the judge held that the balance of
convenience tilted heavily in favour of the CEB “as [APS] is debarred to claim
the amount until all disputes had been cleared on the maxim of ex turpi causa
non oritur actio.” He added that if APS
suffered any damage it would be protected by the undertaking in damages. The Court of Appeal did not address the
balance of convenience at all.
79. The Board is unable to agree with the judge’s approach to
balance of convenience. The Board
accepts the submission made on behalf of APS that the reasons why reported
cases of injunctions being granted (or continued) under the fraud exception are
so rare are (a) because it is almost never possible to establish the test for
fraud as opposed to a mere possibility of fraud, but also (b) because the
balance of convenience will almost always militate against the grant of an
injunction.
80. In Harbottle Kerr J identified the problem thus at p 155:
“The plaintiffs then still
face what seems to me to be an insuperable difficulty. They are seeking to
prevent the bank from paying and debiting their account. It must then follow
that if the bank pays and debits the plaintiffs' account, it is either entitled
to do so or not entitled to do so. To do so would either be in accordance with
the bank's contract with the plaintiffs or a breach of it. If it is in
accordance with the contract, then the plaintiffs have no cause of action
against the bank and, as it seems to me, no possible basis for an injunction
against it. Alternatively, if the threatened payment is in breach of contract,
which the plaintiffs' writs do not even allege and as to which they claim no
declaratory relief, then the plaintiffs would have good claims for damages
against the bank. In that event the injunctions would be inappropriate, because
they interfere with the bank's obligations to the Egyptian banks, because they
might cause greater damage to the bank than the plaintiffs could pay on their
undertaking as to damages, and because the plaintiffs would then have an
adequate remedy in damages. The balance of convenience would in that event be
hopelessly weighted against the plaintiffs.”
81. APS further rely upon the reasoning in Rix J’s judgment in the
Czarnikow- Rionda case at pp 202-204 and, in particular his conclusion at point
(11):
“(11) I do not know that it
can be affirmatively stated that a Court would never, as a matter of balance of
convenience, injunct a bank from making payment under its letter of credit or
performance guarantee obligations in circumstances where a good claim within
the fraud exception was accepted by the Court at a pre-trial stage. I do not
regard Mr. Justice Kerr and the other Courts which have approved or applied the
logic of his ‘insuperable difficulty’ as necessarily saying that it could never
be done. It is perhaps wise to expect the unexpected, even the presently
unforeseeable. All that can be said is that the circumstances in which it
should be done have not so far presented themselves, and that it would of
necessity take extraordinary facts to surmount this difficulty.” The Board agrees.
82. On the facts, the Board accepts the submission made on behalf
of APS that nothing in paras 33-40 of Mr Tulloo’s affirmation of 21 December
2010, where he dealt briefly with the balance of convenience, raises any facts,
let alone extraordinary facts, capable of surmounting the difficulty. Only two
substantive points were advanced by Mr Tulloo.
First, CEB was willing to give a crossundertaking in damages which it
had the means to honour. Second, if no
interim injunction was granted, the CEB would suffer irreparable damage in that
it would be saddled with 660,000 bulbs which were likely to be counterfeit and
which had not been inspected prior to shipment contrary to undertakings given
to the court on 15 November and 3 December 2010. There is no evidence that the bulbs were
likely to be counterfeit. Moreover the
Board has already expressed the view that issues relating to lack of inspection
prior to shipment are matters for arbitration and have no bearing on the
liability of Standard Bank under the letter of credit. Moreover, the CEB has not satisfied the test
for establishing the fraud exception, either on the part of APS or, critically,
on the part of Standard Bank. In any
event neither the CEB nor the judge or the Court of Appeal grappled with the
difficulties identified by Kerr and Rix JJ.
CONCLUSION
83. For these reasons the Board allows the appeal. As to costs, its provisional view is that the
CEB must pay the costs of APS and Standard Bank both before the Board and in
the courts below. The Board will however
consider submissions to the contrary if they are filed within 28 days of the
judgment being handed down. Any
submissions in response should be submitted within 14 days thereafter.
Subscribe to:
Posts (Atom)